- 买家和发展商购买房产。根据分层建筑物的附表H/Schedule H,发展商需要在36个月内交空屋。发展商之后和相关房屋部门申请延长多6个月(42个月)来交空屋。在得到批准后,发展商在08.2017交空屋。
- 买家指发展商没有按照SPA的条款按时交空屋。 他向发展商索赔利息。买家的申请被地方法庭驳回,他随后提出上诉。
- 买家的抗辩点是,联邦法庭在Ang Ming Lee & Ors v Menteri Kesejahteraan Bandar, Perumahan dan Kerajaan Tempatan & Anor and other appeals [2020] 一案中已经说明,隶属房地部的房屋管制处(controller),无权批准任何发展商要求延长交屋期的期限。
- 上诉法庭同意买家的抗辩点,并表示该部门所批准的延长期限,已经抵触附表H/Schedule H,因此无效。Ang Ming Lee & Ors v Menteri Kesejahteraan Bandar, Perumahan dan Kerajaan Tempatan & Anor and other appeals [2020]
- 法庭也强调买卖协议的条款不能抵触附表H/Schedule H… the provisions in the SPA are not merely contractual, but are in effect statutory provisions, as they are actually provisions of sch. H of the Regulations, which have been imposed by law upon the parties.
- 另外,即使发展商是在2016年就和房屋部做出申请,而联邦法庭是在2020年才裁定房屋管制处无权批准任何发展商要求延长交屋期的期限;然而法庭认为,联邦法庭在当时并没有提到追溯适用期限;而且在考量到较早前的案例时,法庭表示Ang Ming Lee一案是适用的…the decision in Ang Ming Lee applied retrospectively… In my view, since the Federal Court in Ang Ming Lee had not specifically directed that its decision was prospective in nature, it applied retrospectively.
- 上诉法庭批准了买家的申请。
*详细的案情和判决,请阅读以下的英文版文章。
The factual background
- Pursuant to a sale and purchase agreement (“SPA”) dated 31.08.2013, the Plaintiffs had purchased from the Defendant, the developer, a unit at A-18-3A, Mosaic SR Tower A, Southkey, Johor Bahru, Johor (“the Unit”) at the price of RM763,000.00.
- Although the SPA was a contract pursuant to Schedule H to the Housing Development (Control & Licensing) Regulations 1989 (“Housing Development Regulations”), Clauses 25 and 27 of the SPA provided for 42 months (instead of 36 months as statutorily prescribed) as the completion period. Time for delivery of vacant possession
- The Defendant subsequently applied for and obtained from the Kementerian Kesejahteraan Bandar, Perumahan dan Kerajaan Tempatan (“the Ministry”), a further extension of six months to deliver vacant possession, which approval was communicated via letter dated 01.12.2016.
- The Defendant had surrendered vacant possession of the Unit on 08.2017 and the common facilities on 31.12.2017, resulting in what the Plaintiffs claimed to be, a delay of 183 days and 306 days respectively, on the basis that delivery of vacant possession should have been on 28.02.2017.
- The Plaintiffs filed their claim on 21.02.2020 for liquidated ascertained damages (“LAD”) in the amount of MYR38,254.52 and MYR12,793.32 for the delay in delivery of the Unit and common facilities respectively.
- On 30.08.2020, the Plaintiffs filed an application for summary judgment, which was dismissed by the Magistrate. As a result thereof, the Plaintiffs appealed to this Court. This Appeal was allowed for the following reasons.
Contentions, evaluation, and findings
- The learned Magistrate concluded that there were triable issues, namely:
(i) whether the Plaintiffs had objected to the initial completion period of 42 months as opposed to 36 months;
(ii) whether the Ministry had the power to extend the completion period for a further six months to 48 months; and
(iii) whether the Plaintiffs, after being informed of the extension, had taken any action against such decision.
- The nub of the Plaintiffs’ contention was that the learned Magistrate had erred when she decided there were triable issues, and that had she considered the Federal Court case of Ang Ming Lee & Ors v. Menteri Kesejahteraan Bandar, Perumahan Dan Kerajaan Tempatan & Anor And Other Appeals [2020] 1 CLJ 162 (“Ang Ming Lee”), she would have allowed the Plaintiffs’ application for summary judgment.
- The Plaintiffs further argued that the SPA, which was a statutory contract, was governed by Schedule H to the Housing Development Regulations, and therefore, the decision of the Ministry to grant an extension of six months, was not valid.
- The relevant provisions for consideration were Section 24 of the Housing Development (Control & Licensing) Act 1966 (“Housing Development Act”), and regulations 11 and 12 of the Housing Development Regulations, all of which read:
Housing Development (Control & Licensing) Act 1966
Section 24 – Powers to make regulations.
(2) In particular and without prejudice to the generality of the foregoing power, the regulations may –
…
(e) regulate and prohibit the conditions and terms of any contract between a licensed housing developer, his agent or nominee and his purchaser;
******
Housing Development (Control & Licensing) Regulations 1989
Regulation 11 – Contract of sale.
(3) Where the Controller is satisfied that owing to special circumstances or hardship or necessity compliance with any of the provisions in the contract of sale is impracticable or unnecessary, he may, by a certificate in writing, waive or modify such provisions:
Regulation 12 – Appeal.
Notwithstanding anything to the contrary in these Regulations, any person aggrieved by the decision of the Controller under paragraph (3) of regulation 3, paragraph (1) of regulation 4, paragraph (4) of regulation 5, paragraph (2) of regulation 9 or paragraph (3) of regulation 11 may, within fourteen (14) days after having been notified of the decision of the Controller, appeal against such decision to the Minister; and the decision of the Minister made thereon shall be final and shall not be questioned in any court.
- In my view, the Plaintiffs were correct in their submission, pursuant to the decision of the Federal Court in Ang Ming Lee, which held that such changes to the statutory contract made by the Ministry were ultra vires Schedule H to the Housing Development Regulations, and, therefore, invalid.
- The opinion of the Federal Court, through Tengku Maimun Tuan Mat CJ on the validity of section 24 of the Housing Development Act and regulation 11 of the Housing Development Regulations are as follows:
“On the above analysis, we hold that the Controller has no power to waive or modify any provision in the Schedule H Contract of Sale because s. 24 of the Act does not confer power on the Minister to make regulations for the purpose of delegating the power to waive or modify the Schedule H Contract of Sale to the Controller. And it is not open to us to read into the section an implied power enabling the Minister to do so. We consequently hold that reg. 11(3) of the Regulations, conferring power on the Controller to waive and modify the terms and conditions of the contract of sale is ultra vires the Act.
- Reference was made also to Sri Damansara Sdn Bhd v. Tribunal Tuntutan Pembeli Rumah [2020] 1 LNS 146:
“As decided in Ang Ming Lee, reg. 11(3) HDR is ultra vires HDA. If reg. 11(3) HDR is invalid, the Controller’s Extension which is made pursuant thereunder, is also invalid.
…
As the Controller’s Extension is invalid (please refer to the above paragraph 19), the 42 Months Period cannot apply in this case. By virtue of reg. 11(1) HDR, the SPA “shall be in the form prescribed in Schedule H”. Consequently, all the parties in this case are bound by the 36 Months Period as provided in Schedule H. This is clear from the use of the mandatory term “shall” in reg. 11(3) HDR.
- As was emphasised in Sri Damansara Sdn Bhd v. Tribunal Tuntutan Pembeli Rumah and Ang Ming Lee, the Housing Development Act and Housing Development Regulations are social legislation, enacted by Parliament to protect home buyers in particular, and not housing developers.
- Reference was also made to the case of Alvin Leong Wai Kuan & Ors v Menteri Kesejahteraan Bandar, Perumahan Dan Kerajaan Tempatan & Ors And Other Applications [2020] 6 CLJ 55, although I am mindful that the Court of Appeal had delivered its decision on 29 July 2021, overruling the decision of the High Court.
- The Defendant’s contention pivoted on the Federal Court case of Ahmad Jefri Mohd Jahri v. Pengarah Kebudayaan & Kesenian Johor & Ors [2010] 5 CLJ 865, where it submitted that the mode to challenge the extension of six months by the Ministry should have been by way of a judicial review of such decision. The Defendant had emphasised that since the Plaintiffs’ claim in the present case was contractual in nature, the decision in Ang Ming Lee had no application, since the Federal Court in that case was addressing an application for judicial review of the Minister’s decision.
- I was unable to agree with the Defendant, bearing in mind that the contract in question was statutory in nature, and as such, strict adherence was necessary. This principle was expounded by the Court of Appeal in Encony Development Sdn Bhd v. Robert Geoffrey Gooch & Anor [2016] 1 CLJ 893, where it was stated:
“The SPA between the respondents and the appellant, who is a housing developer, is governed by a statutory form of contract as prescribed in sch. H of the Housing Development (Control and Licensing) Regulations 1989 [PU(A) 58/1989] (‘the regulations’). As such, the provisions in the SPA are not merely contractual, but are in effect statutory provisions, as they are actually provisions of sch. H of the Regulations, which have been imposed by law upon the parties.”
- Furthermore, the extension of time in question had already been declared void ab initio by the Federal Court in Ang Ming Lee, and as such, there was palpably nothing to challenge, as this Court was bound by the decision in Ang Ming Lee by virtue of the doctrine of stare decisis. In any event, the fact that the Plaintiffs had not applied for a judicial review to challenge the extension did not render such extension valid.
- This brings to the forefront the issue of whether the decision in Ang Ming Lee is retrospective in nature, bearing in mind that the extension by the Ministry was granted via letter dated 01.12.2016, which was prior to the decision of the Federal Court in Ang Ming Lee. In light of cases such as Abillah Labo Khan v. PP [2002] 3 CLJ 521 and Semenyih Jaya Sdn Bhd v. Pentadbir Tanah Daerah Hulu Langat & Another Case [2017] 5 CLJ 526, the answer to that is in the affirmative, that is, the decision in Ang Ming Lee applied retrospectively. The only exception to such principle would be if there was a specific direction of perspectivity expressed in the judgment itself. In my view, since the Federal Court in Ang Ming Lee had not specifically directed that its decision was prospective in nature, it applied retrospectively. Reference was made also to Kok Chay Har & Ors v BH Realty Sdn Bhd [2021] 1 LNS 13, in which the learned Judicial Commissioner in that case had addressed similar issues as those in the present case.
- In the final analysis, it must be remembered that the Housing Development Act and the Housing Development Regulations are social legislation, and as such, regard must be had to the purpose of the legislation as prescribed by Section 17A of the Interpretation Acts 1948 & 1967, which reads:
Section 17A – Regard to be had to the purpose of Act
In the interpretation of a provision of an Act, a construction that would promote the purpose or object underlying the Act (whether that purpose or object is expressly stated in the Act or not) shall be preferred to a construction that would not promote that purpose or object.
- Furthermore, there should be no attempt to rewrite statutory contracts at the expense of purchasers. This was made clear by the Federal Court in Ang Ming Lee in the following passage:
“In the instant appeals, the Schedule H contract of sale prescribed by the Regulations is to carry into effect the provisions of the Act, which is to protect the interests of the purchasers. The regulations made by the Minister must thus achieve the object of protecting the interests of the purchasers and not the interests of the developers. And at the risk of repetition, the duty to protect the interests of the purchasers is entrusted to the Minister.”
- In light of the settled law referred to above, it was my view that the learned Magistrate had erred when she concluded that there were triable issues, resulting in the dismissal of the Plaintiffs’ application for summary judgment.
Conclusion
- This Appeal was allowed with costs.
Source: Teo Siang Hian John & Anor v Southkey City Sdn Bhd [2021] MLJU 2461. High Court Johor Bahru. Evrol Mariette Peters JC.
See also: Murugan a/l Superammuniam v Southkey City Sdn Bhd [2021] MLJU 1950. High Court Johor Bahru. Evrol Mariette Peters JC (Identical Grounds of Judgment)
==============================
*如果您需要聘请律师处理法律事务,您可以联系我们。
*如果您需要法律咨询(付费),您可以联系我们。
*我们的律师楼拥有超过18年的执业经验。我们有处理民事纠纷(打官司/法庭诉讼)、商业纠纷、劳工纠纷(工业法庭)、追讨债务、遗产分配、立遗嘱、离婚、抚养权、赡养费、产业分配、领养小孩、拟商业合约、拟雇佣协议、拟买卖合约、银行贷款、法律咨询、法律顾问、等法律事务。全马的案件,我们皆有处理。*We have more than 18 years of experience in the legal profession. We handle matters such as civil litigation, commercial disputes, labour disputes (Industrial Court), debt recovery, probate & letter of administration, will, divorce, children custody, maintenance/alimony, adoption, distribution of matrimonial assets, drafting commercial agreement, drafting employment contract, drafting sale and purchase agreement, process loan documentations, legal consultation, legal advisory, miscellaneous legal works.
*Wilson Kuek律师是“法律与你同行 Law & Justice”面子书群组的创办人。“法律与你同行”是马来西亚最大的法律平台。我们的平台每天为无数的平民百姓免费解除各类的法律困扰。
*加入 我们的“法律与你同行”FB 群组: http://bit.ly/fblawnjustice
*Like 我们的“法律与你同行” FB Page: http://bit.ly/lawnjusticefbpage
*加入我们的Telegram:
(i) 各项法律/政府政策: https://t.me/LawAndJusticeGroup
(ii) 雇主必知的法律/政府政策: https://t.me/LawAndJusticeEmployer
*订阅我们的YouTube: http://bit.ly/lawnjustice
*Kuek, Ong & Associates. Advocates & Solicitors. No.86-1, Jalan Mahagoni 1, Bandar Botanic, 41200 Klang, Selangor Darul Ehsan.
#Kuek, Ong & Associates #Kuek Ong & Associates #Kuek Ong Associates #Klang Legal Firm #Klang Lawyer #KL Lawyer #Kuala Lumpur Lawyer #Chinese Lawyer in Malaysia #Malaysia Lawyer #Litigation Lawyer #Divorce Lawyer #reputable lawyer #trustworthy lawyer
#郭汪律师事务所 #郭汪律师楼 #巴生律师楼 #吧生律师楼 #马来西亚华人律师 #懂华文的律师 #懂华语的律师 #KL律师 #吉隆坡律师 #民事诉讼律师 #民事案律师 #专打官司的律师 #专打官司律师 #工业法庭律师 #劳工法庭律师 #专打离婚案的律师 #专打离婚案律师 #处理离婚的律师 #处理离婚案的律师 #离婚律师 #买卖合约律师 #有经验的律师 #好律师 #专业的律师 #信得过的律师 #利害的律师 #有信誉的律师 #有声望的律师 #出名的律师 #有名的律师 #有实力的律师
#发展商迟交房子 #发展商迟交屋子 #发展商迟交公寓 #延期 #extension of time